Project: Northern Columbus Loop Project, Phase VI
Company: Columbia Gas of Ohio, Inc.
Case No.: 04-1621-GA-BTX
Location: Franklin County to Delaware County
Status: Staff is monitoring final construction activities
The project involves the installation of a 6.7 mile natural gas pipeline through southern Delaware County. Pipe diameter ranges from 24 inches at the eastern tie-in with Phase V, to 12 inches at the southwestern terminus. This pipeline project is associated with the pipeline project proposed in Case No. 04-1620-GA-BTX (Phases IV and V of the Northern Columbus Loop Project). Both projects are part of the Applicant’s long term plan to continue to provide gas service to the rapidly growing northern Columbus and southern Delaware County region. The Board certificated the application on August 3, 2005. Construction was completed and the pipeline placed into service on June 27, 2006.
Other Information:
Opinion, Order, and Certificate