18-1293-EL-BTX: Timber Road IV Wind Farm Transmission Line

Case number: 18-1293-EL-BTX
Project: Timber Road IV Wind Farm Transmission Line
Applicant: Paulding Wind Farm IV
Location: Paulding County
Status: Hearings

The purpose of the transmission line is to support the Timber Road IV Wind Farm, which is currently pending before the Board in Case No. 18-0091-EL-BGN. The proposed transmission line would run from the Timber Road IV Wind Farm substation to the existing Timber Road III generation lead line. The transmission line would be a 138 kilovolt overhead line that would be approximately 2.9 miles long.

Local public hearing
March 5, 2019, at 6 p.m.
Ohio State University Extension Building
503 Fairground Dr.
Paulding, Ohio 45879

Adjudicatory hearing
March 19, 2019, at 10 a.m.
Offices of the Public Utilities Commission of Ohio
Hearing Room 11-D
180 E. Broad St.
Columbus, Ohio 43215

Participate and stay informed