18-1335-EL-BTX: ATSI Wood County 138 kV Reinforcement Project

Case number: 18-1335-EL-BTX
Project: Wood County 138 kV Reinforcement Project
Applicant: American Transmission Systems, Inc.
Location: Wood County
Status: Approved

The applicant will construct improvements to the transmission system in Wood County. The project will consist of a new 6-mile long 138 kilovolt (kV) transmission line extending from the existing Lemoyne-Midway 138 kV Transmission Line to the existing Brim Substation. 

Transmisison line map

Participate and stay informed