Ohio Power Siting Board, Monday, March 3, 2008

OHIO POWER SITING BOARD

MEETING

March 3, 2008

3:30 PM, Room 11E

A G E N D A

 

  1.  Approval of the minutes of the regular Board meeting of November 26, 2007.
  2. Case No. 00-1527-EL-BGN, Consideration of the Application of Calpine Corporation   to transfer a Certificate of Environmental Compatibility and Public Need for a Merchant, Combined Cycle 704 Megawatt Power Plant in Fremont, Ohio to FirstEnergy Generation Corp.
  3. Case No. 06-1358-EL-BGN, Consideration of the Application of American Municipal Power-Ohio, for a Certificate of Environmental Compatibility and Public Need for an Electric Generation Station and Related Facilities in Meigs County, Ohio.
  4. Case No. 07-1305-GA-BTA, Consideration of the Application of Duke Energy Ohio for an Amendment to its Certificate of Environmental Compatibility and Public Need for the C338 Ohio River to Bethel Natural Gas Pipeline Project.
  5. Staff Update.
  6. Presentation by Emily Smith, OPSB Staff Environmental Specialist.