Ohio Power Siting Board Meeting

OHIO POWER SITING BOARD MEETING

Thursday, January 14, 2016

3:30 PM, Room 11B

AGENDA

  1. Approval of the minutes of the regular Ohio Power Siting Board meeting held November 12, 2015.

  2. Case Number 11-4886-EL-BGN.  NextEra Energy Honey Creek Wind, LLC to Site a Wind-Powered Electric Generation Facility in Seneca and Crawford Counties, Ohio. (Entry Considering Request to Withdraw Application)

  3. Case Number 12-1981-GE-BRO.  OPSB Rules. Revision to turbine setback rule. (Entry on Rehearing)

  4. Case Number 15-1682-EL-BTA.  Amendment to Biers Run-Hopetown-Delano Transmission Line Project filed by AEP Ohio Transmission Company, Inc. (Order on Certificate Amendment)

  5. Case Number 11-2400-EL-BGN.  Ashtabula Wind Energy, LLC to Site a Wind-Powered Electric Generation Facility in Ashtabula County, Ohio. (Entry Considering the Status of the Case)

  6. Case Number 12-2933-EL-BGN.  Republic Wind, LLC to Construct a Wind-Powered Electric Generation Facility in Seneca and Sandusky Counties, Ohio. (Entry Considering the Status of the Case)