12-1361-EL-BSB: Biers Run Substation Project, Ross County

Case No.: 12-1361-EL-BSB
Project:     Biers Run Substation Project
Company: American Electric Power Transco
Location:  Ross County
Status:      Operational

This application is for a 345/138/69 kV switching substation project located 4 miles northwest of Chillicothe, Ohio. On Sept. 30, 2013, the Board certificated construction at the preferred site, and the facility became operational on December 1, 2016.