Media Contact: Matt Butler (614) 644-7670
The OPSB will hold a hearing in New Matamoras, Ohio on April 16, 2018 to allow the public to express their views about AEP Ohio Transmission Company’s proposal to build a new 138 kilovolt electric transmission line spanning southern Monroe County and northeastern Washington County.
The OPSB will hold a local public hearing on June 4, 2018 to allow the public to express their views about AEP Ohio Transmission Company’s proposal to build a new 138 kilovolt electric transmission line in eastern Washington County.
The OPSB will hold a hearing on June 4, 2018 to allow the public to express their views about AEP Ohio Transmission Company’s proposal to rebuild approximately 4.8 miles of its existing Berlin-Ross 69 kilovolt (kV) transmission line to 138 kV standards.
The OPSB today authorized the construction of solar-powered electric generating facilities in Brown and Hardin counties. The two projects are the first of their kind reviewed by the OPSB and would become the largest solar farms in Ohio once constructed.
The OPSB will hold a hearing on April 5, 2017 to allow the public to express their views about Harrison Power LLC’s proposal to construct a 1,050 megawatt natural gas-fired electric generating facility in Cadiz, Ohio.
The OPSB today authorized AEP Ohio Transmission Company to construct two electric transmission line projects in southeastern Ohio.
The OPSB today authorized Clean Energy Future-Oregon, LLC to construct a 955 megawatt natural gas-fired, combined-cycle electric generation facility in Lucas County.
The OPSB has postponed two hearings previously scheduled regarding Vinton Solar Energy, LLC’s proposal to construct a solar-powered electric generation facility in Vinton County. The OPSB will reschedule the hearings at a later date.
The OPSB has postponed the adjudicatory hearing previously scheduled for Icebreaker Windpower, Inc.’s application to construct a wind-powered electric generation facility in Lake Erie. The OPSB will reschedule the adjudicatory hearing at a later date.
The OPSB will hold a hearing in Lower Salem, Ohio on Nov. 1, 2017 to allow members of the public to express their views about AEP Ohio Transmission Company’s proposal to construct an electric transmission line in Washington County.
The OPSB will hold a hearing in Kenton, Ohio on Dec. 6, 2017 to allow members of the public to express their views about Hardin Solar Energy LLC’s proposal to construct a solar-powered electric generation facility in Hardin County.
The Ohio Power Siting Board (OPSB) has postponed the two hearings previously scheduled for AEP Ohio Transmission Company’s (AEP Ohio Transco) proposal to construct an electric transmission line in Washington County. The OPSB will reschedule the hearings at a later date.
The OPSB today separately authorized the construction of natural gas-fired, combined cycle generation facilities in Guernsey and Trumbull counties. The two facilities will add 2,040 megawatts of generation capacity to the regional transmission grid.
The OPSB will hold a hearing in McArthur, Ohio on Dec. 5, 2017 to allow members of the public to express their views about Vinton Solar Energy, LLC’s proposal to construct a solar-powered electric generation facility in Vinton County.
The OPSB will hold a hearing in Bellaire, Ohio on Nov. 14, 2017 to allow members of the public to express their views about AEP Ohio Transmission Company’s proposed West Bellaire-Glencoe 138 kilovolt Transmission Line Rebuild Project .
The OPSB will hold a hearing in Mount Orab, Ohio on Nov. 30, 2017 to allow members of the public to express their views about Hillcrest Solar I, LLC’s proposal to construct a solar-powered electric generation facility in Brown County.
The OPSB has postponed the adjudicatory hearing previously scheduled for Duke Energy Ohio’s proposal to construct a natural gas pipeline extension in Hamilton County and will reschedule the hearing at a later date.
The OPSB will hold a hearing in Lower Salem, Ohio on Oct. 10, 2017 to allow the public to express their views about AEP Ohio Transmission Company’s proposal to construct a new electric transmission line in Washington County.
The Ohio Power Siting Board (OPSB) today separately authorized American Transmission Systems, Inc. (ATSI) and AEP Ohio Transmission Company (AEP Ohio Transco) to construct three new electric transmission lines in Clark and Monroe counties.
The OPSB will hold a hearing in Cleveland on Nov. 8, 2017 to allow the public to express their views about Icebreaker Windpower, Inc.’s application to construct a wind-powered electric generation facility in Lake Erie.