16-0702-EL-BTX: AEP Macksburg-Devola 138 kV Transmission Line Rebuild Project

Case Number: 16-0702-EL-BTX
Project: Macksburg-Devola 138 kV Transmission Line Rebuild Project
Applicant: AEP Ohio Transmission Company
Location: Washington County
Status: Approved

The Macksburg-Devola transmission line is part of the overall Marietta Area Improvements Project. The existing 23 kilovolt (kV) infrastructure has reached an age where it is in need of rebuild and redesign to improve reliability for customers across the region. The approximately 17-mile long Macksburg-Devola transmission line will be rebuilt to 138 kV, connecting the Macksburg Substation to the Devola Substation. 

Participate and stay informed